Offshore Produced waterMPPE for Inpex Ichthys Gas Produced Water - Australia
MPPE for removal of:
- Dispersed and dissolved oil (aliphatics)
- Dispersed and dissolved aromatics (BTEX)
- Poly Aromatic Hydrocarbons (PAHs)
- Environmental impact reduction 95-99%
- Max flow rate 180 m3/h (2x 90 m3/h)
- 2 parallel MPPE trains creates 100% redundancy for practically the whole operation period
Inpex Ichthys LNG project:
- Largest discovery of hydrocarbon liquids in Australia in 40 years
- Inpex Ichthys will make Australia the world's first or second LNG exporting country by 2020
- MPPE helps to achieve the strictest environmental conditions set to date worldwide
- Planned delivery 2013 and planned start up 2016
click here for the print version
Offshore Produced waterMPPE unit for first Floating LNG plant in the world - Shell Prelude - Australia
MPPE for removal of:
- Dispersed oil (aliphatics)
- Dissolved and dispersed aromatics (BTEX)
- Poly Aromatics (PAHs)
Specifications
- Flow rate: 140 m3/h
- >99% removal of BTEX, PAHs, Aliphatics (oil)
Shell Prelude Project:
- First Floating LNG plant in the world
- FLNG technology reduces project costs and the environmental footprint of an LNG development
- Delivery April 2013
- Direct discharge after MPPE treatment
click here for the printversion
Why MPPE for FLNG
1) Zero Harmful Discharge
2) Robustness
3) Remote controlled MPPE Operations
4) Removal of dissolved and dispersed oil (aliphatics), aromatics (BTEX), Polyaromatic Hydrocarbons (PAHs), Naphtalenes, Phenantrenes, Dibenzothiophenes(NPDs)
5) Offshore Gas produced Water: more than 30 years accumulated experience.
6)References: Shell FLNGPRELUDE, Statoil Kollsnes, Statoil/Shell OrmenLange, Woodside PLUTO,
NAM (Shell/Exxon) K15A, K15B,TOTAL F15A, Vermilion (TOTAL) Harlingen
Click here for printversion
Offshore Produced waterStatoilHydro Kollsnes Norway, MPPE for removing toxic load of gas produced water
MPPE for Removal of:
- Dispersed oil (aliphatics)
- Dissolved and dispersed aromatics (BTEX)
- Poly Aromatics (PAHs)
Specifications:
- Flowrate 20 m3/hr
- Includes Steam Generator and RO unit
- >99% removal of BTEX, PAHs, Aliphatics (oil)
Kollsness project general:
Produced water treatment of 5 offshore gas fields. Exsisting biological water treatment collapsed due to toxicity of produced water. After upstream installation of mobile MPPE unit the biological water treatment recovered within 3 months. The mobile MPPE unit removes toxic dissolved and dispersed oil, Aliphatics, Aromatics (BTEX) and PAHs. The mobile unit is running since 2005 and now replaced by permanent unit indicated below.
Click here for the printversion.